How to Frame A Deck from Start to Finish (A DIY Step-by-Step Guide for Framing a Deck by Yourself)

How to Frame a Deck

Whenever I think of Building a Deck, the framing process is always what comes to mind. And this makes sense because framing the deck is 70% of the entire deck building process!

The good news is that deck framing is not inherently difficult. The bad news is that you will be working with large lumber (and a lot of it). 

Pro Tip: Deck framing goes much more smoothly if you have a second set of hands helping you. However, it is possible to frame a deck entirely by yourself (which is what I had to do for this 95% of this deck).ย 

Note that the deck framing process is sometimes easier to understand visually. So if you are more of a visual learner, consider watching my โ€œHow to Frame a Deck YouTube Videoโ€ Linked below.ย 

My YouTube video shows the entire deck framing process from start to finish.
Check out my โ€œHow to Frame a Deckโ€ YouTube video for additional information on the entire Deck Framing Process

Now this is a long article becasue it is very detailed (so bear with me) – Let’s begin!

Tools and Materials Needed to Frame a Deck

Below are some of the most common tools and materials that will be needed to frame a deck:ย 

Deck Framing โ€œAnatomyโ€ (Understanding all the Components) 

Before you can actually frame a deck, you must ensure that you understand all of the deck framing components. Refer to the image below which illustrates all of the framing components for a typical deck.ย 

The โ€œAnatomyโ€ of any Deck framing Projectย 
The โ€œAnatomyโ€ of any Deck framing Projectย 

Within this article, I am going to show you how to install each of the deck components in the image above so that you can frame you deck like a professional.ย 

How to Install a Deck Ledger Board

The ledger board is the horizontal framing member that attaches to your house and carries one end of your joists. Itโ€™s one of the most critical structural elements of the deck โ€“ as it is also the most common โ€œfailure pointโ€ for decks. 

If the ledger fails, the deck fails.
If the ledger isnโ€™t flashed properly, the house rots.

Lovelyโ€ฆ 

You are going to be attaching your Ledger Board to your homeโ€™s existing Rim Joist โ€“ so you need to ensure that the rim joist is in good condition. If you are replacing an existing deck, remove the old ledger board and flashing and inspect the Rim Joist. If you are building a new Deck from Scratch, your homeโ€™s Rim joist is likely in good condition โ€“ but you will likely need to remove the siding and flashing to access it.ย ย Fortunately, my homeโ€™s rim joist is still in good condition โ€“ so we can proceed with the ledger board installation process.ย 

Here is a look at my Homeโ€™s Rim Joist โ€“ not in perfect condition, but no too bad.ย 
Here is a look at my Homeโ€™s Rim Joist โ€“ not in perfect condition, but no too bad.ย 

PRO TIP: If your homeโ€™s Rim joist is fully rotted out, you have a repair job on your hands that is beyond the scope of this article. However, there is a way to frame a deck without a ledger board. To do this, you will actually install a Beam directly at the house. Instead of attaching the Joists to your house, this Beam will support the joists instead โ€“ giving you a โ€œfreestandingโ€ deck. Refer to the image below. 

Example of a โ€œBeam at Houseโ€ Installation Instead of a Ledger Board
Example of a โ€œBeam at Houseโ€ Installation Instead of a Ledger Board

Waterproofing Your Homeโ€™s Rim Joist

Before you even think about hanging the ledger board, your want to protect the homeโ€™s Rim Joist from water. There are many different waterproofing membranes / flashings that you can use to accomplish this, but I applied a peel-and-stick underlayment (GAF ice-and-water style membrane) directly to the rim joist of the house:

Apply the Waterproof Membrane to your Homeโ€™s Rim Joist (I like to leave it long and then trim it to size with a Utility Knife)ย 
Apply the Waterproof Membrane to your Homeโ€™s Rim Joist (I like to leave it long and then trim it to size with a Utility Knife)ย 

The goal here is simple – If water ever gets behind our ledger, we want it to contact our waterproof membrane, not our homeโ€™s Rim Joist (or the structural lumber behind it!).

Once the flashing is applied, we can mark the height for the ledger board. 

Setting the Ledger Board Height

To set the height of the ledger board, I like to use a laser level

Set the Hight of the Ledger Board using a Laser Level (you can also use a 6โ€™ level..)ย 
Set the Hight of the Ledger Board using a Laser Level (you can also use a 6โ€™ level..)ย 

I like to set my Ledger Board 2โ€-3โ€ below the door threshold for the following reasons: 

  • This will give space for our 1โ€ decking boards to be installed on top of the ledger board and joists.ย 
  • The additional 2″ drop helps ensure that under heavy rain, water doesnโ€™t sneak into the house.

Adjust your laser level so that the projected level line is ~3โ€ below the door threshold. This will be the mounting height for the top of the ledger board. 

Pro Tip:ย Laser levels are amazingโ€ฆ until the batteries die, sunlight washes them out, or someone bumps into them. Always snap a chalk line once youโ€™re happy with the laser projection.

I highly recommend that you go back and snap a chalk line over top of your laser level line
I highly recommend that you go back and snap a chalk line over top of your laser level line

Installing the Ledger Board

Ledger boards are typically 2ร—8โ€, 2ร—10โ€, or 2×12โ€ pressure-treated lumber. Typically, your ledger board size will match your joist size. 

Before installing the ledger board (or any board on your deck), you will want to โ€œcrownโ€ your lumber (more on that in the joist section). For now, just know: crown up.

Below are the Steps for Hanging the Leger Board: 

Tack the Ledger Board in Place with a Framing Nailer and Double Check level using a 6โ€™ level (having a second person is very helpful)

Tack the ledger board in place with some nails
Tack the ledger board in place with some nails

These 3โ€ framing nails are temporary โ€“ The real structural connection comes later with ledger screws or structural fasteners.

Ledger Board Waterproofing and Flashing 

With the Ledger board tacked in place, itโ€™s time to waterproof the ledger like our long-term happiness depends on itโ€ฆ because it does.

Flashing on Top of the Ledger

First, I apply a 6″ wide strip of flashing tape on top of the ledger board:

Apply a 6โ€ Piece of Waterproof Flashing the Overhangs the Ledger Board and Goes up Vertically against the House
Apply a 6โ€ Piece of Waterproof Flashing the Overhangs the Ledger Board and Goes up Vertically against the House

Ledger โ€œZโ€ Flashing (Metal or Vinyl)

Next comes the main piece of flashing that covers the joint between the wall and the ledger:

Place Vinyl or Metal Ledger Flashing on top of the Ledger Board and Nail it in placeย 
Place Vinyl or Metal Ledger Flashing on top of the Ledger Board and Nail it in placeย 

Iโ€™m using metal flashing because thatโ€™s what was available locally, but vinyl is often easier to work with (you can cut it with scissors or a utility knife).

I fasten the flashing to the wall every 18″โ€“24″ or so using a roofing nailer (or just a hammer and roofing nails).

If your deck is longer than 8′, youโ€™ll likely need multiple pieces of flashing. To Join two pieces of flashing together:

If you need to overlap sections of Flashing, apply a bead of Calk and overlap by ~4โ€ย 
If you need to overlap sections of Flashing, apply a bead of Calk and overlap by ~4โ€ย 

This way, any water that runs along the flashing will flow over the joint, not under it.

Final Flashing Layer โ€” Joist Tape Over Nail Holes

Now you might be thinking:

โ€œOkay, now there are nail holes in the flashing. Isnโ€™t that a problem?โ€

Well, yesโ€ฆ thatโ€™s why I runย a final piece ofย joist tapeย (flashing tape) along the top of the ledger and over the nail line of the metal flashing. This will Seal the nail penetrations and add one final waterproof layer.

Apply a piece of flashing tape over any of the nail holes that were used to attach the ledger board to the home
Apply a piece of flashing tape over any of the nail holes that were used to attach the ledger board to the home

Structurally Fastening the Ledger

With the ledger board waterproofed, itโ€™s time to make the ledger structural.

Iโ€™m usingย PowerPro LedgerTiteย screws, 3โ…” long. These are structural screws specifically designed for securing ledger boards.

I installed two structural screws in between each 16โ€ โ€œJoist Bayโ€
I installed two structural screws in between each 16โ€ โ€œJoist Bayโ€

General best practices (always check your specific code and manufacturer instructions):

  • Follow spacing and pattern requirements from your local code / deck guide.
  • I installed the screws roughly everyย 12″โ€“16″, withย two screws between each joist bay, staggered vertically (one high, one low).

Before driving these screws, I highly recommend that you mark your 16โ€ O.C. Joist Spacing on your Ledger Board before installing the structural screws

This saves you from trying to drive joist hanger nails into hardened structural screws later.

At this point, the ledger board has been secured with structural screws and we can begin installing the Posts and Beams.  

How to Install the Deck Posts and Beams (Building the Primary Support Structure)

With the ledger in place, we shift our focus to the outer support system: posts and beams.

Setting The Post Height Using a Laser Level

The goal is for the top of each beam to be at the same height as the bottom of the ledger board โ€“ this way your joists will sit level from the house to the beam.

Since weโ€™re using 2ร—8 joists, the bottom of the joist aligns with the bottom of the ledger. Thatโ€™s our reference point for post height. 

First, establish a laser line that is even with the bottom of the Ledger Board .

Establish a Laser Level Line that is Even with the Bottom of the Ledger Board
Establish a Laser Level Line that is Even with the Bottom of the Ledger Board

Below are the Steps that I used to mark my Post Height: 

Stand aย 6ร—6 postย in the post base hardware on the concrete footer. Use a Post Level to make sure the Posts are perfectly Plumb.ย 

Stand up the Posts in the Post Hardware
Stand up the Posts in the Post Hardware

Mark where the laser line intersects with the post and mark where the line hits the post.ย 

Mark where the laser line project on the posts
Mark where the laser line project on the posts

That mark indicates where the bottom of the joist needs to be, and will indicate the cut line for your post. 

Cut the posts to height with aย miter sawโ€”usually cutting one side, then flipping and cutting the other side of the post is required to the 6โ€ร—6โ€ thickness.

Cut the Posts to the right height using a Miter Saw (or similar)ย 
Cut the Posts to the right height using a Miter Saw (or similar)ย 

On this deck, I chose 6โ€ร—6โ€ posts instead of 4โ€ร—4โ€ posts for added stiffness and peace of mind, especially considering the future load of a hot tub.

Beam Connection Methods โ€“ Why Notching Wins

Next up, we need to think about how we are going to attach the beams to the posts.

There are three common methods:

  1. Side mounting beams to the post with hardware (DO NOT USE)
    • Beam is bolted to the side of the post
    • Puts a lot of stress on the hardware
    • Less direct load transfer
    • Increasingly frowned upon or prohibited in many jurisdictions
Don't use side mounting to attach the beams to the posts
  1. Sitting the beam directly on top of the post with hardware
    • Good load transfer (beam bearing on post)
    • Uses post caps or similar hardware
Setting the beam on top of the post is acceptable
  1. Notching the post and nesting the beam in the notch
    • Beam bears directly on the remaining post section
    • Provides excellent load transfer and lateral restraint
    • Strong, clean, and my preferred method
Notching the post to fit the beam is the method I recommend.

For this deck, weโ€™re using the third method: notched posts.

For more information on the various options for attaching the Deck Beam to a Post, Check out my Blog Article Linked here. 

Notching the 6โ€ร—6โ€ Posts for the Double 2ร—10 Beam

For my deck, I am using a beam made from twoย 2ร—10 boardsย (called a double 2ร—10)

I am Using a 2โ€x10โ€ Beam for my Deck
I am Using a 2โ€x10โ€ Beam for my Deck

Note that there are many different deck beam size options and that you may want to use a different deck beam type / size for your deck. 

Measuring the Notch

First, determine the actual depth of your beam:

My Beam will be approximately 9.5โ€ Tall
My Beam will be approximately 9.5โ€ Tall

Then:

  1. Markย 9ยฝ” downย from the top of the post on the face.
  2. Transfer that mark around both sides of the post to outline theย heightย of the notch.
  3. Next, mark theย thicknessย of the beam notch:
    • Each 2ร—10 is about 1ยฝ” thick
    • So, two together =ย 3″ย total
    • I markedย 3ยผ”ย to give just a hair of extra clearance so the beam would โ€œnestโ€ easily.

Youโ€™re essentially drawing aย 3″ (or 3ยผ”) deep by 9ยฝ” tallย rectangle on the top side of each post.

Mark the Cutout for the Beam Notch
Mark the Cutout for the Beam Notch

Cutting the Notch

To cut the notch, follow the process below:

Make passes with a circular saw to "start" the notch cut
Make passes with a circular saw to “start” the notch cut

First, cut the Beam Notch Using a Circular Saw. Next, finish the cut using a reciprocating saw.

You May need to clean-up your cuts using a Sawzall if your circular saw does not cut deep enough
You May need to clean-up your cuts using a Sawzall if your circular saw does not cut deep enough

Finally, I also trimmed about ยฝ” from the top of the post so the beam would sit slightly proud of the post, rather than the post sticking above the beam.

Treating Cut Ends of Pressure-Treated Lumber

Any time you cut pressure-treated lumber, it is recommended that you apply anย end-cut treatmentย (a liquid wood preservative for PT lumber) to all fresh cuts.This helps maintain rot resistance where the factory treatment has been cut away.

I recommend that you apply a wood preservative to all of your cut ends
I recommend that you apply a wood preservative to all of your cut ends

Assembling and Installing the Beams

Once the posts are notched and ready, we bring in the beams.

Building the Beam

  • Pick two 2ร—10s that are similar in depth.
  • Lay them side by side and line them up.
  • Nail them together withย 3″ framing nailsย (space them every 16″โ€“24″).
  • You can come back later and add structural screws, but nails are fine to get everything in position.
Nail the 2โ€x10โ€ Double Beam Together with a Few Framing Nailsย 
Nail the 2โ€x10โ€ Double Beam Together with a Few Framing Nailsย 

Next, itโ€™s time lift the Beams and position them in place. This is a two-person lift if you can get help. If not, move methodically and be prepared for some awkward (and Heavy) moments.

Lift the Beam(s) into place and position it on top of the Post Notches
Lift the Beam(s) into place and position it on top of the Post Notches
  • Set the beams on the notches at the tops of the posts.
  • Make minor adjustments so the edges line up with your layout.
  • Ensure each beam segment has anyย splices directly over posts, per code.
Lift the Beam(s) into place and position it on top of the Post Notches
Lift the Beam(s) into place and position it on top of the Post Notches

What matters is that when youโ€™re done:

  • The beam is fully seated in each notch.
  • The tops of the beams line up level with the ledger board.
  • All posts are still plumb.

Securing the Beams to the Posts

There are two Primary methods for attaching the Beams to the Posts:

Old-school method:

  • Drill aย โ…” holeย through the beam and post.
  • Useย ยฝ” carriage boltsย with washers and nuts.
  • Tighten everything down.
Anchor Bolt Method for Attaching Beams to Posts
Anchor Bolt Method for Attaching Beams to Posts

Modern method (which I used):

  • Useย Thru-Lok style structural fasteners
  • No pre-drilling required.
  • Drive from one side, add washers and nuts as required, and tighten from the screw side.
Thru-Bolt Method For Attaching Posts to Beamsย 
Thru-Bolt Method For Attaching Posts to Beamsย 

Youโ€™ll need:

  • Two fasteners per post-beam connection,
  • Orย fourย where thereโ€™s a beam splice at the post.
Note that you Will Need 4 Bolts at any Beam Splice Connection
Note that you Will Need 4 Bolts at any Beam Splice Connection

Before tightening everything down, use a post level to confirm your posts are plumb in both directions.

Finally, to help extend the life of the beam, Apply a strip ofย 6″ flashing tapeย over the top of the double 2ร—10 beam.

Consider waterproofing your deck beams with flashing tape
Consider waterproofing your deck beams with flashing tape

This prevents water from sitting between the two boards, which could otherwise encourage rot over time.

With the Beams in place and waterproofed, itโ€™s time to install the Joists. 

How to Install the Deck Joists

If you didnโ€™t mark you joist spacing as part of the ledger board installation, you will want to mark all of your joist locations now. Joists are typically installed 16โ€ On Center (O.C.) but sometimes 12โ€ O.C. (or even 24โ€ O.C. Joist Spacing is used).ย 

It helps to mark the joist spacing on your ledger boards and beams at the start
It helps to mark the joist spacing on your ledger boards and beams at the start

I Highly Recommend that You Mark all of you Joist Locations on the Ledger Board and Your Beam Before you Install the First Joist

Itโ€™s a good idea to mark both the Ledger Board and the Beam at the same time to ensure that all of your joists are spaced evenly and marked in the right place. 

Starting with the Outermost Joist

I start with the outermost joist, because:

  • It defines the outer edge of the deck.
  • Itโ€™s used as a reference to square the whole joist layout.

For the outermost joist:

I used a concealed Joist Hanger for the Outermost Joists Only
I used a concealed Joist Hanger for the Outermost Joists Only

This outermost joist needs to be perfectly perpendicular to the ledger.

To confirm that, I used the 3-4-5- triangle method:

Ensure the the outermost joist is sqaure to the ledger board
Ensure the the outermost joist is sqaure to the ledger board

Ensure that the Outermost Joist Is Perfectly Square from the House by using the Right Triangle Method (3-4-5, 6-8-10, etc.) 

Every joist must beย crowned before installation – here is what that means..

Crowning the Joists

  • Look down the long edge of the board.
  • Identify the slight โ€œarchโ€ or bow.
  • Installย all joists with the crown facing up.

If some joists are crowned up and some crowned down, your finished deck surface will have humps and dips. Not goodโ€ฆ

I like to โ€œCrownโ€ all of my joists at the Same Time. Install all boards โ€œCrown Upโ€
I like to โ€œCrownโ€ all of my joists at the Same Time. Install all boards โ€œCrown Upโ€

The Best Joist Installation Method (In My Opinion)

After trying a few awkward methods (like trying to hold the joist in the hanger and nail it at the same time), I landed on a simple, efficient process:

  1. Place the joist at the ledger so theย top of the joist is flush with the top of the ledger board.
  2. Align the joist with your layout line on the ledger.
  3. Shoot aย framing nail through the top of the joist into the ledger. This acts as aย temporary clamp.
Position the Joist even with the Top of the Ledger Board and Tack it in Place with a Framing Nail
Position the Joist even with the Top of the Ledger Board and Tack it in Place with a Framing Nail
  1. Now the joist is hanging hands-free exactly where it needs to be.
  2. Take your time and install theย joist hangerย around the joist:
    • Use the necessary nails or structural screws per joist hanger manufacturerโ€™s requirements
    • I used a combination ofย joist hanger nails and screws
Place the Joist Hanger Around the Beam and Fasten using the approved screws / nails
Place the Joist Hanger Around the Beam and Fasten using the approved screws / nails

On the beam side:

  • Useย hurricane tiesย or other approved connectors to secure the joist to the beam.
I like to use a palm nailer to nail the hurricane ties to the beams (it's way faster)
I like to use a palm nailer to nail the hurricane ties to the beams (it’s way faster)

Use Hurricane Ties (or Joist Hangers) to attach the Joists to the Beams (Ensure 16โ€ O.C. Spacing that matches the ledger board layout

Repeat for each joist:

  • Crown up
  • Align with layout
  • Tack from the top
  • Install hanger
  • Secure to beam

Itโ€™s repetitive, but once you get into a rhythm, it goes quickly.

Multi-Beam / Multi-Span Joist Strategies

Most decks just have one beam and a single span โ€“ But for my deck, I installed multiple beams to support a future Hot-Tub. To do this, I โ€œsisteredโ€ the joists together on the first beam and then used additional hurricane ties to secure the joist to the additional beams. 

Installl addition hurricane ties as needed

I โ€œSisteredโ€ the Joists Together on the First Beam

Installing all of this hardware can be cumbersome

I used additional Hurricane Ties, etc. as needed to secure the Joists to the additional Beams

Cutting the Ends of the Joists to Size (If Needed)

I typically like to leave all of my joists long and โ€œun-cutโ€ until I install my decking boards. So I will cover this more during the โ€œDecking Installationโ€ Section. However, you will likely need to cut the end of your joists at some point. I like to mark all of the cut locations on the joists and then cut them to size (from above), using a circular saw.ย 

Cut all of your Joists to the Appropriate Length
Cut all of your Joists to the Appropriate Length

As noted, I will go into more detail on the best method for cutting the joists in the โ€œDeckingโ€ section of this Ebook. 

Installing the Rim Joist

Once all joists are cut to the correct length, you will need to install the Rim Joist. Below is the best way to install a rim joist if you are working Alone: 

This makes it way easier to install the Rim Joist if you are working by yoruself.
This makes it way easier to install the Rim Joist if you are working by yoruself.

Tack a Piece of Scrap Wood to the Boom of the Joist to help hold the Rim Joist in Place while you install It

  1. Lift the rim joist into position and rest it on the blocking.
  2. Nail the rim joist to the end of each stud using a framing nailer.
Nail the Rim Joist to the ends of the Joists
Nail the Rim Joist to the ends of the Joists
  1. Later, go back and addย screwsย for extra peace of mind.

If the rim joist needs to be spliced:

  • Install blocking at the joint so each rim piece has full bearing at the connection point (Refer to the left side of the image above)

Crown the rim joist and treat any cut ends with end-cut preservative, just like the other structural members.

How To Install Deck Blocking

Before we walk away from framing, there are a few locations where support โ€œblockingโ€ should be installed. 

Mid-Span Blocking

If your joist span exceeds about 8 feet, itโ€™s recommended to add blocking between the joists. The blocking will:

  • Reduce twisting and racking
  • Help distribute loads
  • Make the deck feel more solid underfoot

I like to stagger the blocking so itโ€™s easier to nail, but you can alsoย toe-nailย or use screws from the side.

Mid-Span Blocking is a Good Idea to Help your Deck to feel More Sturdy
Mid-Span Blocking is a Good Idea to Help your Deck to feel More Sturdy

Horizontal Blocking for Railing Posts

If you are going to be installing a railing or if you are going to be โ€œPicture Framingโ€ your deck (discussed in more detail later), I highly recommend that you consider installing flat blocking around the perimeter of your deck. 

Consider installing Flat Blocking around the Perimeter of Your Deck
Consider installing Flat Blocking around the Perimeter of Your Deck

On previous decks, I skipped this step and I had to crawl underneath the Deck to add blocking directly under railing postsโ€ฆ It worked, but it was a pain.

On this deck, I pre-installed horizontal blocking everywhere that Iโ€™d need railing posts.

If your deck is longer than your decking boards (e.g., > 16′), you may want to use aย breaker boardย instead of butt joints (discussed more in the next section).

The above represents โ€œBreaker Boardsโ€ in the Decking โ€“ which we will need to support from below
The above represents โ€œBreaker Boardsโ€ in the Decking โ€“ which we will need support from below

To support a breaker board:

  • Installย extra blockingย at the breaker board location
  • This ensures each end of the decking boards and the breaker board itself have solid support.
Install Flat Blocking anywhere you plan on installing a Breaker Board
Install Flat Blocking anywhere you plan on installing a Breaker Board

By planning this during framing, you avoid awkward retrofits later.

Here is a look at the Framed Deck with all of the blocking installed
Here is a look at the Framed Deck with all of the blocking installed

Installing Joist Tape and Final Waterproofing (Donโ€™t skip!)

Although Pressure-treated lumber might last 20โ€“25 years, Composite decking often has warranties around 30โ€“35 years. So to try and make our pressure treated lumber last as long as the composite decking above it, I recommend installing joist tape. 

Joist tape is applied to the top of the joists and helps to shed water and moisture away from the wood. Trapped water between the joists and the decking is the biggest cause of rot โ€“ so this joist tape will help a ton.ย 

Apply Joist Tape to the Top of Every Joist
Apply Joist Tape to the Top of Every Joist

Additionally Ensure that you apply waterproofing to all of your flat blocking as well.ย 

Apply Additional Waterproofing to all of your Flat Blocking
Apply Additional Waterproofing to all of your Flat Blocking

Run all of your waterproofing flashing continuously over all of yourย blockingย andย breaker board supportsย too.

Here is a Look at the Deck with all of the Waterproofing Installed
Here is a Look at the Deck with all of the Waterproofing Installed

Will joist tape magically add decades of life to your deck? Hard to prove. But in the context of the time and money invested into a big deck, a few extra rolls of tape feel like a smart insurance policy. If you want more of an explanation on if joist tape is actually worth it, you can check out my Blog Article Linked here.ย 

Conclusion

At this point, you know exactly how to frame a deck from start to finish! Although no part of the deck framing process is exceptionally difficult, it takes quite a lot of work to frame a deck (especially if you are working by yourself). 

Although this article give a good overview of the entire deck framing process, I highly encourage you to watch my โ€œHow to Frame a Deck from Start to Finishโ€ YouTube video linked below: 

This video showcases the entire deck framing process and I can all but guarantee that it will help you to avoid making common mistakes. 

I hope this article helped! If you would like additional information on Deck Building, check out myย โ€œHow to Build a Deckโ€ YouTube series. I promise that it will be super helpful.ย 

DISCLAIMER: This is a reference guide only. Consult local code requirements. Links included in this article might be affiliate links. If you purchase a product or service with the links that I provide, I may receive a small commission. There is no additional charge to you! Thank you for supporting ATimprovements so I can continue to provide you with free content each week!